Project Background

Reprovisioning of Diamond Hill Crematorium is divided into two phases. Works to be executed in Phase I and II include the following major items:

 

Phase I

·        Demolition of facilities in Existing Crematorium in the southern side of the Project site, including

·        Existing siting out area

·        Garden of remembrance

·        Existing building structure, including CLP secondary substation, toilets, pavilion and retaining walls

·        Construction of the New Crematorium main facilities, including

·        One cremator plant room housing six cremators

·        Three fuel tanks (with total capacity of 34,000L)

·        Two service halls (each can hold 120 people)

·        One pulverizing room

·        One mortuary

·        One office

·        Toilets for public

·        Ancillary service rooms including battery fork lift, transformer and switch room, emergency generator room and joss burners

·        Two automatic transportation systems for coffins and part of an underground service tunnel for coffin circulation

·        Vehicular loading bay for coffin van, coach

·        Landscape area

·        Dangerous goods store

·        Installation of temporary CLP electricity transformer at Phase II boundary

 

Phase II

·        Demolition of Existing Crematorium main facilities, including:

  • Two service halls
  • One cremation room with six cremators
  • One transformer room
  • One underground oil fuel storage tank
  • One mortuary
  • One machine room
  • One general store plus water tank
  • One dangerous good store
  • One chimney (10m in height)

·        Construction of the rest of the New Crematorium, including:

  • Two service halls (each can hold 120 sample)
  • Two automatic transportation systems for coffins and part of an underground service tunnel for coffin circulation
  • Vehicular loading bay for coffin van, coach etc
  • Landscape area

 